Create a Website Account - Manage notification subscriptions, save form progress and more.
Updates/Letters To Residents:
Engineer: CobbFendley
Preliminary Engineering Report - PER
Project Status: Construction Phase 7
Town Hall Meeting: March 5, 2024, 6 p.m. Meeting Presentation
Notice to Proceed Date: April 29, 2024 NTP letter
Contract Award Date: 2-27-2024
Estimated Start Date: 2024
Project Duration: 365 Days Initial Construction Schedule
Updated Construction Schedule March 2025: Updated Schedule * based on current contract additional days due to weather or change order
Contract Amount: $6,250,674.50
BID Documents: https://www.civcastusa.com/project/6579b618e933374d36a43b94/summary
Brighton Place Plans : /DocumentCenter/View/2436
Updates/Letters to Residents:
Sample Letter/Project Map
Town Hall Meeting Notice
Town Hall Presentation
Town Hall: November 20, 2025
Plan set: Merlin and Spring Oaks 100%
Preliminary Schedule: Schedule Merlin & Spring Oaks
Project: Pavement & Utility Improvement Project
Status: Preliminary Engineer Report, design 30%
#2 Wild Oak Area